Driving modes and rigging for on-road driving
6.5 Installing/removing the outrigger beams
Operating Instructions GMK5250L 3 302 633 en 6 - 39
27.09.2017
6. Screw in the spacers; à p. 6 - 47.
7. If necessary put outrigger pads into position;
à p. 6 - 43.
8. Mount all necessary outrigger beams in the same way in accordance
with this checklist.
9. If the truck crane is at the site:
Extend the outrigger beams to the necessary outrigger span, secure
them and stabilize the truck crane.
10. If the truck crane still has to be driven to the site:
Fully retract and secure the outrigger beams.
à Extending/retracting outrigger beams, p. 11 - 45.