VTrak E-Class Product Manual
332
Rebuild marks logical
drive synchronized upon
rebuild completion
Result of successful rebuild. Normal.
Redundancy Check
Redundancy Check is
started
Redundancy Check has started manually or by
schedule.
Redundancy Check is
completed
Redundancy Check has finished.
Redundancy Check is
paused
Redundancy Check paused because of user
intervention, schedule or a higher priority background
activity.
Redundancy Check is
resumed
Redundancy Check has resumed again after a
pause.
Redundancy Check is
stopped
Redundancy Check stopped because of user
intervention, schedule or the logical drive was deleted
or went critical or offline.
Redundancy Check is
aborted due to internal
error
System resources are low. Reduce system load or
restart the VTrak. See page 119 or page 245.
Redundancy Check
encountered inconsistent
block(s)
Check the logical drive’s inconsistent block table. See
page 156 or page 205. Rebuild the disk array if
necessary. See page 148 or page 196.
Redundancy Check task
is queued
Redundancy Check has been set manually or by
schedule.
Redundancy Check task
is stopped internally
The logical drive is offline. See page 336.
Resource
Resource is NOT
available
System resources are low. Reduce system load or
restart the VTrak. See page 119 or page 245.
Spare Check
Spare check started on
the given spare drive
Result of settings or user action. Normal.
Spare check completed
successfully on the given
spare drive
Normal.