Rigging work
11.1 Rigging work checklists for crane operation with the main boom
11 - 4 3 302 633 en Operating Instructions GMK5250L
27.09.2017
15. Install the lifting limit switch; Ã p. 11 - 120.
16. Install anemometer, air traffic control light and camera on main boom;
à Anemometer and air traffic control light, p. 11 - 126,
à Camera on main boom, p. 11 - 137.
17. Perform all the required checks prior to crane operation;
à CHECKLIST: Checks before operating the crane, p. 10 - 1.
18. Enter and confirm the current rigging mode;
à p. 10 - 32.
19. With the RCL adjusted accordingly, rig the counterweight combination
required for the operation according to
Lifting capacity table;
à CHECKLIST: Rigging the counterweight, p. 11 - 74.
20. If required, mount the auxiliary hoist;
à CHECKLIST: Installing the
auxiliary hoist
, p. 6 - 55.
21. Enter the current rigging mode with the new rigged counterweight
combination at the RCL display;
à p. 10 - 32.