Crane operation
10.1 Before operating the crane
Operating Instructions GMK5250L 3 302 633 en 10 - 3
27.09.2017
9. Check the position of the hoist ropes; Ã p. 10 - 6.
10. Compare current rigging mode with the
RCL display – enter and con-
firm current rigging mode, if necessary;
à p. 10 - 30.
11. Check the telescope status;
à Checks before starting work, p. 10 - 96.
12. – Switch off the slewing gear for 0° and 180° working positions –
symbol (1) red;
à p. 10 - 119.
– Switch off houselock for other working positions – symbol (2) is red;
à p. 10 - 19.
13. Check the electrical system for correct operation;
à p. 10 - 7.
s