210 Upgrade and Maintenance Manual TX300 S8 / RX350 S8
Hard disk drives / solid state drives
7.2.6.4 Concluding steps
Ê When working on a tower server, close the HDD bay cover as described in
section "Installing accessible drive and HDD bay covers" on page 105.
Ê Please observe the notes on RAID rebuild in section "Performing a RAID
array rebuild" on page 153.
7.2.7 Removing 2.5-inch HDD / SSD modules
7.2.7.1 Preliminary steps
Ê If the HDD / SSD module to be removed is combined into a RAID array,
please proceed as follows:
Customer Replaceable Unit
(CRU)
Average task duration:
5 minutes
Tools: tool-less
RAID level Procedure
RAID 0
Only remove an HDD module combined in a RAID 0
array if defective.
V CAUTION!
Removing an operational HDD module will
result in data loss!
RAID 1
RAID 5
Removing an HDD module from a RAID 1 or RAID 5
array will not result in data loss.
However, the removed drive needs to be replaced
immediately by an HDD module of the same or larger
capacity.
I After replacing the HDD module, RAID rebuild
will be performed as a background process as
described in section "Performing a RAID array
rebuild" on page 153.

Table of Contents

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the Fujitsu PRIMERGY TX300 S8 and is the answer not in the manual?

Fujitsu PRIMERGY TX300 S8 Specifications

General IconGeneral
BrandFujitsu
ModelPRIMERGY TX300 S8
CategoryServer
LanguageEnglish

Related product manuals