4 Transport, installation and commissioning
Commissioning
Page
4 - 32
MB-20-G/MB-200G-W_MB-LABmaster_MB-200 MOD_TP700
Operating Manual - V5.0 - 04/2018 - STD
To achieve a purity of 100 ppm, the required consumption of purge gas (=working gas)
should be 11.5 times the glovebox volume.
Manual purge
The manual purge must be performed on all the components, including built-in options
such as a freezer etc.
During a manual inertisation (purging) of the glovebox, a flexible reinforced hose, that is
guided through an opening into the glovebox interior, transfers working gas to the interior.
The opening can be a flange on the rear of the glovebox.
This ensures the presence of a pure atmosphere after the commissioning purge process.
Otherwise the residual ambient air will cause a long-term decreased quality of the glove-
box atmosphere until the natural gas exchange takes place.
Safety
DANGER
Inert gas displaces oxygen in the room
Risk of suffocation
Make sure, that the requirements to the clear room volume are followed. Make suffi-
cient room volume available.
Make sure that the room is sufficient ventilated.
Prerequisites
¡ All connections have been made properly.
¡ Analysers are still switched off, the system functions “Circulation” and “Regeneration”
are not activated and the freezer is switched off.
¡ All antechamber doors are closed.
¡ The connections for manual purging have been made (refer to Connecting the system
[}4 - 21]).
¡ Sufficient working gas (purge gas) is available.
¡ The freezer and other equipment must be at room temperature.