Levelling
At the end of the ventilation phase, the chamber is brought back to atmospheric pressure (LEVELLING) by injecting sterile outside air to allow the
opening of the door and the retrieval of the load:
1 134°C POROUS
LEVELLING
86.9 °C
-0.43 bar 29:21
CHAMBER
Water
tank
DESCRIPTION
STATUSES
(P, t)
VP WP
EV1
(no)
EV2
(nc)
EV3
(nc)
EV4
EV5
(no)
EV6
(nc)
Fan
Levelling
(pressure)
from -0,45 to –0,10 bar
(-0,10 bar to the value of 0 bar in the
memory)
OFF OFF ON OFF OFF OFF OFF OFF OFF
Levelling
(waiting time for the
release of the locking
door mechanism)
Waiting time = 15”
(counting start from pressure–0,10 bar)
OFF OFF ON OFF OFF OFF OFF OFF OFF