Event codes
418 (428) 9836 3123 01
23.1.9 E800-E899 Software events
This event indicates that the RBU revision
is not supported by the controller (for
example an RBU bronze in a PF Graph
controller), the RBU is missing, or the
RBU license file is missing or corrupt.
Acknowledge the event.
Check that the correct RBU is
connected to PF.
If the event reappears, then upgrade the
PF software.
Error condition
detected by
software
An error condition was detected in
software.
Power Focus: The probable cause is that an
external application has started too many
subscriptions.
STB: Software error
Power Focus: Close external programs
connected to Power Focus.
STB: Return tool to service.
Database must be cleared, db version
is not correct
Tightening initialization phase failed.
Hardwar e failure.
Acknowledge the event.
Contact the Atlas Copco service
representative.
No calibration was received from the drive
during the tightening initialization phase
(timeout 100 ms).
Acknowledge the event.
Check tool cable.
Reboot PF.
No tightening result was received from the
drive before the cycle abort timeout.
If necessary, increase the P144 Cycle
abort timer in Pset.
Autoset could not be executed. The
calculated angle was too small.
Acknowledge the event.
Program the Pset manually or by
Quick programming.
The Autoset could not be executed, four
NOK tightenings were performed.
Acknowledge the event.
Program the Pset manually or by
Quick programming.
Autoset rejected
Pset in CCW
direction
Auto set is only permitted on a CW Pset.
Program the Pset manually or by
Quick programming.
If Quick programming is used, then
change the direction from CW to CCW
after programming.
Feature Not
Available In
Software
Revision
This event is displayed when an attempt is
made to run Multistage with a RBU
bronze, or handle a Pset with a PsetID
larger than the max number of Psets.
Reconfigure to an allowed