4
Equipment Installation
In this chapter:
4.1 Precauons
4.2 Site Selecon
4.3 Unpack and Inspect Equipment
4.4 Adjustable Range of Rack Brackets
4.5 Install 19-Inch, 2-Post Rack Rail Kit
4.6 Install 23-Inch, 2-Post Rack Rail Kit
4.7 Install 19-Inch, 4-Post Rack Rail Kit
4.8 Install 23-Inch, 4-Post Rack Rail Kit
4.9 Install Power Terminal Adapter
4.10 Install Blade in Housing
4.11 Recer and Blade Wiring Connecons
4.12 Install Power Cables
4.13 Install Fan Unit
4.14 Install Plug-In Unit
4.15 Install SFP Module
4.16 Install Filler Panel
4.17 Install Data Communicaon Network Cabling
4.18 Install Local Management Port Cabling
4.19 Install CD ROADM Cabling
4.20 Install L160 Raman Cabling
The procedures described in this secon are used to install L100 Blades, PIUs, pluggable modules, and other
required equipment in 19- or 23-inch, 2- or 4-post racks or the 1FINITY Housing.
The following tools and equipment are required:
Common hand tools
Digital Mulmeter (DMM)
Terminal lugs (for rack installaon)