Step 4
Provision pass-through connecons between two CD ROADM degrees.
Commands:
% set port-connection PASS-THRH-1 src-shelf 2 src-slot 0 src-subslot 0 src-port C2
dst-shelf 1 dst-slot 0 dst-subslot 0 dst-port C2
% set port-connection PASS-THRH-2 src-shelf 1 src-slot 0 src-subslot 0 src-port C2
dst-shelf 2 dst-slot 0 dst-subslot 0 dst-port C2
Connue with the next task.
Addional Instrucons:
Perform the same procedure for each pass-through connecon to be provisioned.
7.11.4
Provision Cross-Connects
Step 1
Provision a DROP cross-connect from an OCH on an edge port of an L100 Blade to a client port on a PIL1-3PS2
PIU.
Command:
% set fabric och-connection XCON-DROP src-if ots-2/0/0/E1 src-och 1 dst-if
och-3/1/0/C1
Step 2
Provision a ADD cross-connect from a client port on a PIL1-3PS2 to an OCH on an edge port of an L100 Blade.
Command:
% set fabric och-connection XCON-ADD src-if och-3/1/0/C1 dst-if ots-2/0/0/E1 dst-
och 1
Step 3
Provision pass-through cross-connects between two CD ROADM degrees.
Commands:
% set fabric och-connection XCON-PASS-1 src-if ots-1/0/0/E1 src-och 2 dst-if
ots-2/0/0/E1 dst-och 2
% set fabric och-connection XCON-PASS-2 src-if ots-2/0/0/E1 src-och 2 dst-if
ots-1/0/0/E1 dst-och 2
✓ This task is complete.
ROADM Turn-Up and Operations
Adding Degree to ROADM Node
270
Release 19.1.1 · Issue 1.1, May 2021
Fujitsu and Fujitsu Customer Use Only

Table of Contents

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the Fujitsu 1FINITY L100 and is the answer not in the manual?

Fujitsu 1FINITY L100 Specifications

General IconGeneral
BrandFujitsu
Model1FINITY L100
CategoryServer
LanguageEnglish

Related product manuals