CX2550/60/70 M4 Upgrade and Maintenance Manual 69
Basic hardware procedures
4.17 Switching on the server node
V CAUTION!
For further safety information, see chapter "Important information" on
page 33.
Ê If applicable, connect all external cables to the server node.
Ê Press the On/Off button either on the server node or on the corresponding
front panel to start up the server node.
Then the Power indicator lights up green.
I For more information, see section "Controls and indicators on the
server node" on page 448.
4.18 Concluding software tasks
Ê Perform the following software tasks to put the server back in operation:
"Verifying the system time settings" on page 92
"Viewing and clearing the System Event Log (SEL)" on page 93
"Updating the NIC configuration file in a Linux and VMware environment"
on page 94
"Performing a RAID array rebuild" on page 97
"Looking up changed MAC/WWN addresses" on page 97