2-22 Return to Section Topics 4200-900-01 Rev. K / February 2017
Section 2: Model 4200-SCS Software Environment Model 4200-SCS User’s Manual
Tests (ITMs and UTMs)
A check mark can be inserted or removed for any test.
Inserting a check mark for a test also inserts a check mark for its device plan, its subsite
plan, and the project plan.
Device plan
Clearing a check mark for a device plan also clears the check marks for all of its subordinate
tests.
Inserting a check mark for a device plan also inserts check marks for all of its tests.
Removing the check marks for all the tests in the device plan, also removes the check mark
for the device plan.
Subsite plan
Removing a check mark for a subsite plan also removes the check marks for all of its device
plans and tests.
Inserting a check mark for a subsite plan also inserts check marks for all of its device plans
and tests.
Removing the check marks for all the tests in the subsite plan, also removes the check mark
for the subsite plan.
Initialization and termination steps
Removing a check mark for initialization or termination steps also removes the check marks
for all of its UTMs.
Inserting a check mark for initialization or termination steps also inserts check marks for all
of its UTMs.
Removing the check marks for all the UTMs in the initialization or termination steps, also
removes the check mark for the initialization or termination steps.
Project plan
Removing a check mark for a project plan also removes the check marks for all of its plans
and tests.
Inserting a check mark for a project plan also inserts check marks for all of its plans and
tests.
Removing the check marks for all the tests in the project, also removes the check mark for
the project plan.
NOTE Reference manual, Figure 6-16 shows an example of project plan structure that
shows a mix of enabled and disabled tests.

Table of Contents

Other manuals for Keithley 4200-SCS

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the Keithley 4200-SCS and is the answer not in the manual?

Keithley 4200-SCS Specifications

General IconGeneral
BrandKeithley
Model4200-SCS
CategorySemiconductors
LanguageEnglish