Page 262 Chapter 9 - Planned Maintenance (PM)
9.2 Maintenance of Cables and Connectors
Table 9-1 provides descriptions and frequencies of the Discovery LS procedures for maintenance
of cables and connectors.
Table 9-3: Maintenance Procedures of Cables and Connectors
Description of Procedure
Frequency
Comment
Visual inspection and verification of all table bulkhead connections. 1 Year
Visual inspection and verification of all the cable connections of cables on the
gantry side of the table retractor.
1 Year
Visual inspection and verification of all cables connected to new A36-1, A36-2,
and A37-1 panels on the back of the PET Gantry.
1 Year See
Section
7.5.3.
Visual inspection and verification of all PET and CT E-Stop cable connections.
1 Year
Visual and manual inspection and verification of all the grounding connections.
Important: Make sure that all grounding cables are firmly connected by
testing them manually.