4. Shut down power to the router by pressing the AC input switch or DC circuit breaker
for all power supplies to the off (O) position.
5. Disconnect power from the router.
6. Remove the cables that connect to all external devices.
7. Remove all field replaceable units (FRUs) from the router.
8. Remove the router from the rack:
If you are using a mechanical lift, place the lift platform under the router, unscrew
and remove the mounting screws from the rack, and move the router to the shipping
crate.
If you are not using a mechanical lift and the router weight is fully supported by a
shelf or another router, unscrew and remove the mounting screws from the rack.
Three people can then lift the router and move it to the shipping crate.
If you are not using a mechanical lift and the router weight is not fully supported by
a shelf or another router, three people should grasp the router while a fourth person
unscrews and removes the mounting screws from the rack. The three lifters can
then move the router to the shipping container.
9. Place the router in the shipping crate or onto the pallet. If on a pallet, bolt the router
to the pallet.
10. Cover the router with an ESD bag and place the packing foam on top of and around
the router.
11. Replace the accessory box on top of the packing foam.
12. Securely tape the box closed or place the crate cover over the router.
13. Write the RMA number on the exterior of the box to ensure proper tracking.