EasyManua.ls Logo

GE Vivid S6 N - 7-4-6-2-6 ACW HPF Test

GE Vivid S6 N
834 pages
To Next Page IconTo Next Page
To Next Page IconTo Next Page
To Previous Page IconTo Previous Page
To Previous Page IconTo Previous Page
Loading...
GE
P
ART NUMBER FN091065, REVISION 2 VS5 N AND VS6 N SERVICE MANUAL
7-84 Section 7-4 - Performing Front End (FE) Diagnostics
PRELIMINARY
7-4-6 Probe Select Board Diagnostic Tests (cont’d)
7-4-6-2-6 ACW HPF Test
NOTE: For a description of this test, refer to the information in “ACW HPF Test” on page 7-14.
NOTE: When performing this test, no probe should be connected to the system and nothing should be touching
the probe connectors!
1.) In the Diagnostic Test window, trackball to ACW HPF Test in the list of ACW tests available for
selection from the Diagnostic Test Tree (see Figure 7-53 "ACW HPF Test" on page 7-84) and press
Set. The ACW HPF Test name is displayed under Execute; the relevant system components to be
tested are highlighted light blue in the Schematic View (PIB & PSB), as shown below:
2.) As indicated in the Special Instructions area, disconnect any probes currently connected to the
system and make sure that nothing is touching the probe connectors.
3.) Adjacent to On Fail, select either Stop or Continue, as required. Stopping on failure enables you
to review a failed test, the moment it fails. Alternatively, you may prefer testing to continue on failure
and later you may review the report.
NOTICE
In order to access an individual board test, it is necessary to insert the service dongle from system boot-
up and enter the Service Password.
NOTICE
It is necessary to disable the Loop option where it should not be used.
After performing this test, you must re-boot the system and perform the DC Offset Calibration procedure
as described in “DC Offset Calibration” on page 7-27.
Figure 7-53 ACW HPF Test