GE
P
ART NUMBER FN091065, REVISION 2 VS5 N AND VS6 N SERVICE MANUAL
Chapter 7 - Diagnostics/Troubleshooting 7-101
PRELIMINARY
• Red: Problems were identified in these components during the performance of the test.
• Yellow: The tests executed so far on these components have passed, but not all
recommended tests have been performed.
5.) At any stage, trackball to the Pause button and press Set, if required.
6.) To resume testing (from the point where you paused), trackball to the Start button and press Set.
When the Temperatures Test sequence is complete:
- the Diagnostic Test window displays the Finished message
- the View Test Log window opens automatically, listing all tests performed and showing details
of which tests passed or failed, as shown in the example in Figure 7-68 "View Test Log -
Temperatures Test" on page 7-102.