X35 ConsoleGeneral Operations
8.20
3. Engage the hydraulic power to Fan 1 circuit.
Refer to your Air Seeder manual, for detailed
information
on calibration.
4. Prime the metering augers (fill each metering
auger with product).
a. Go to the air seeder tank.
b. Turn on calibration valve to start
calibration drive motor.
c. Set the calibration pails under each
metering auger, that is being calibrated.
d. Locate the tank mounted remote calibration
keypad.
i.
If the calibration keypad is disabled,
the buttons on the screen or the in-
cab keypad can be used.
e. Press the tank button to turn on the tanks
that are to be calibrated.
i. This will also actuate the
corresponding tanks on the
calibration screen (the state button
will turn green).
f. Turn on the Master Switch to run the
meters until all are primed /filled.
i.
While
priming, the shaft revolutions
and weight will be accumulated, refer
to Figure 8.37.
g. Turn the Master Switch OFF.
h. Hold the PRIME/RESET button until the
green light flashes.
i. This will reset the pulses,
accumulated auger shaft revolutions
and expected weight for actual
calibration.
Important
It is very important to get a complete reset of
the calibration screen before continuing the
calibration. Always hold prime/reset button until
a green light flashes. The LED on the Reset
button will be amber when there are pulses on the
calibration screen and will turn red once they are
reset to zero.
Figure 8.37 - Revolutions/Weight Accumulated
Reset All
Use buttons in this column to
reset accumulated revolutions
and weight for each tank
Figure 8.38 - Resetting Tanks

Table of Contents