Installation Overview — SH1R Shelf
For commissioning procedures, see the appropriate software document.
See Related Documents for the list of available documents.
l General Electrical Safety Guidelines and Warnings
l Installation Safety Guidelines and Warnings
l Electrical Safety Guidelines and Warnings
l Service Personnel Assumptions
Installation Overview — SH1R Shelf
When you install an SH1R shelf, be sure that you follow the installation procedures in the
proper sequence. This table is an installation procedure checklist, showing the
procedures in the order in which they should occur.
Before installing the equipment, be aware of important rack and
accessory installation requirements. See Supported Rack
Requirements and Accessory Installation Requirements for more
information.
Before proceeding with the installation and cabling, be aware of
standard safety practices and the hazards involved in working with
electrical circuitry to prevent accidents.
Check Installation Procedure
Unpacking an SH1R Shelf
Inspecting the HD Equipment
Installing the Mid-Mounting Brackets on an SH1R Shelf
Installing the Mounting Brackets on SH1R Guide Rails
Connecting the Grounding Terminals
Mounting the SH1R Shelf to a Rack
Installing the CEM
Installing the ECM
Installing the FTM-3 in the SH1R
Installing the PSM-AC3 in the SH1R
Installing a Traffic Module
Installing a QSFPPluggable Transceiver
Installing the Slot Covers
Connecting the Infrastructure Modules
Connecting ACPower to theSH1R Shelf
Inspecting and Cleaning Fiber-optic Connectors and Receptacles
FSP 3000R7 High-Density Subshelf Guide - R17.2 - Issue:B 238