32 01-6203-01R3, CG Drives & Automation
4. Commissioning
4.1. Important notes
WARNING!
Incorrect wiring can cause unexpected states during the commissioning phase.
Possible consequence: death, severe injuries or damage to property
Check the following before switching on the mains voltage:
Is the wiring complete and correct?
Are there no short circuits and earth faults?
Is the motor circuit configuration (star/delta) adapted to the output voltage of the inverter?
Is the motor connected in-phase (direction of rotation)?
Does the "emergency stop" function of the entire plant operate correctly?
WARNING!
Incorrect settings during commissioning may cause unexpected and dangerous motor and system movements.
Possible consequence: death, severe injuries or damage to property
Clear hazardous area.
Observe safety instructions and safety clearances.