Lists/Tables/Plans/Diagrams/Maintenance Verification
Maintenance table
534 / 564
Maintenance interval
Maintenance work
before har-
vest
start
daily
after the
first 50
oper. hrs.
every 50
oper. hrs.
after the
first 500
oper. hrs.
every 500
oper. hrs.
when
needed
annu-
ally
Elevator
Check tension of the elevator belt,
possibly tighten
X X
Cross conveyors
Check tension cross conveyor chains,
possibly tighten
X X
Check tension drive chains,
possibly tighten
X X
Oil drive chains every 100 oper. hrs.
Unload elevator
Tighten the belt X
Bunker floor, all conveyors, elevator shafts, remaining machine
Remove soiling
and sticking dirt
X X
Others
Refill grease container X X
Grease lubricating points according to lubricating plan
Retighten wheel bolts 450 Nm after the first 10 and the first 50 oper. hrs.
Check tire pressure X X
Air conditioning system
Check condenser for soiling, possibly
clean
X
X
Check hoses and lines for chafe marks
(visually), possibly have them
exchanged
X X
Check coolant, possibly have refilled X X
Have the air conditioning system
checked by a qualified workshop and, in
case of need, repaired
X X
Have the collector dryer and coolant
replaced
every 2 years