Material setup 6 Field-IQ crop input control setup
4.
You are returned to the Implement Lift Setup screen to complete the settings.
Setting Explanation
Number of Switches Number of implement switches connected to the Field-IQ
system
Min Changed Switches Number of switch changes required to show the implement in a
lifted state.
For example, if three switches are hooked up to the Field-IQ
system and this setting is set to two, the system must see two
switches in the lifted position before the implement displays as
lifted on the display.
5.
Tap when done.
Material setup
1. At the Implement screen, tap Material Setup.
2. At the Material Setup screen, tap New Material.
3. At the Material Management screen,tap Material Type.
4. At the Material Type screen, select the material type.
ll Row Crop Seed (see Row Crop Seed setup, 124)
l Liquid
l Granular Seed
l Granular Fertilizer
l Anhydrous
5.
Tap to return to the Material Management screen. Here you can set up the material you
chose at the Material Type screen.
Version 7.0, Revision A CFX-750 Display User Guide 123