Cordex®CXCHPControllerSoftwareManual|7-Invertersystems
7.3. Assign a T2S module
EachinvertersystemrequiresoneassignedT2Smodule.IftheT2S Assignment Rule wassetto
Automatic duringsystemcreation,thenaT2Smoduleisautomaticallyassignedoncediscoveredonthe
CANbus.
IftheT2S Assignment Rule wassettoManual,gotoSystems > Inverter System > Inventory > T2Ss,
andselectAssign intheModules Available for Assignment table.
Notice: It can take several minutes to discover a T2S module on the CAN bus, for the first time.
7.4. Commission an inverter system
Onceaninvertersystemhasbeencreated,andaT2Sinvertercontrollerhasbeenassignedtothe
system,itcanbecommissioned.Therearethreestagestocommissioning:
•
Settingthesystemoptions
• Commissioningseedinverters
• Addinginverters
Setting system options
Thiswizardrequeststhefollowingconfigurationinformation:
•
OutputVoltage
• Frequency
• ACPhases
• DCInputGroups
• DCCommissioning
Output voltage canbesetto120Vor230V.Refertothesystemspecificationstodeterminewhich
voltagesettingiscorrect.Theoutputvoltagenormallymatchestheinputvoltage.
Frequency canbesetto60Hzor50Hzisthesameforbothinputandoutput.Refertothesystem
specificationstodeterminewithfrequencyiscorrect.DCCommissioningcanbesettoNoorYes.
NormallyACisinputispresentandthisshouldbesettoNo.
Important: It is important that these values are correct for the proper operation of system
commissioning, and for adding new inverters.
Commission seed inverters
Thesecondstageofcommissioninginvolvesinsertingoneseedinverterforeachphase.Theseed
inverterprovidesareferenceforallotherinvertersinthesamephasesotheycanlearntheirpower
Page 108 0350058-J0 Rev AL