Converting a tower model to a rack model
Ê Carefully turn the server upside down.
I At least two people are needed to turn over a fully equipped server.
Remove hard disk drives and power supply modules in order to
facilitate the task.
Ê Secure the accessible drive cage with two screws.
I Note the correct screw positions: The screw hole on the right that has
been used in the tower configuration remains empty.
Ê Install the front panel module as described in section "Installing the front
panel module" on page 336.
Ê If applicable, install all accessible drives as described in section "Installing
an accessible drive" on page 282.
Ê If applicable, install an HDD extension box as described in section "Installing
an HDD extension box" on page 172.
Preparing the intrusion switch
Ê Remove the intrusion switch module as described in section "Removing the
defective intrusion switch cable" on page 410.
I It is not neccessary to disconnect the intrusion switch cable from the
system board.
Ê Attach a rubber bumper to the front intrusion switch and reinstall the
intrusion switch module as described in section "Installing the new intrusion
switch cable" on page 412.
Reinstalling accessible drives
Ê Reinstall the front panel (rotated by 90 degrees) as described in section
"Installing the front panel module" on page 336.
Ê Reinstall all accessible drives into their original bays (rotated by 90
degrees). Reconnect the cables (see section "Cabling plans" on page 405).
Ê Reinstall all accessible drive filler covers and front covers as described in
section "Installing accessible drive dummy covers" on page 286.