6 RECOVERY, LOADING AND TRANSPORT
6.6 MHL360 E
►
Rigging with a D-link (241/5) size 20 DIN
82101 is recommended, as appropriate for
the weight of the machine.
►
Lower the loading equipment and retract
the dipperstick up to the stop. In this posi-
tion, the load is distributed fairly evenly in
relation to the lifting points.
►
Move all control levers into the neutral posi-
tion.
►
Engage parking brake and swing brake.
►
Switch off the diesel engine. Remove igni-
tion key.
►
Before leaving the driver's seat, flip up the
left armrest.
►
Lock all doors, covers and hoods.
►
The minimum lifting capacity per rope must
be 200 kN. The four slinging ropes (242/1)
must not be shorter than 13 m because of
the load distribution. Only use an ade-
quately sized lifting harness.
►
The ropes must be routed so that no dam-
age is caused to the cab or lining.
►
Carefully hoist the loading machine using
the crane.
BSB50887
(103,170)
46 800MHL360
(147,700)
67 000MHL380
MHL350 35 500
(78,260)
MHL340 29 000
(63,930)
MHL335 25 000
(55,110)
MHL331 23 500
(51,800)
(41,880)
(lb)
kg
19 000MHL320
kg (lb)
Fig. 242 Lifting the machine