Chapter 4 - Functional Checks 4-15
4-3-3-4 Complete power down
1.) If not already in read mode, freeze the image.
2.) When you shutdown the system, enter the scan screen and lightly press the Power On/Off switch
(see: Figure 4-14) once. The System-Exit window is displayed.
Figure 4-14 Power OFF User Interface
3.) Select the SHUTDOWN button. The system performs an automatic full shutdown sequence.
4.) Switch OFF the Circuit Breaker at the rear of the system.
NOTE: The mains outlet of the system for peripheral auxiliary equipment are commonly switched with the ON/
OFF button. So the auxiliary equipment need not to be switched ON/OFF separately.
5.) After complete power down, unscrew the 2 screws and remove the pull-out protection to disconnect
the main power cable from the system or unplug it from the AC wall outlet socket.
6.) Press on the brakes to block the front caster wheels.
7.) Disconnect probes.
NOTICE
!! NOTICE:
After turning off a system, wait at least 10 seconds before turning it on again. The system may not be
able to boot if power is recycled too quickly.
WARNING
WARNING
!! WARNING:
Disconnection of the Main Power Cable is necessary!
For Example: When repairing the system.
NOTICE
!! NOTICE:
Be sure to follow probe handling instruction and caution outlined in Basic User Manual.

Table of Contents

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the GE LOGIQ S7 Pro and is the answer not in the manual?

GE LOGIQ S7 Pro Specifications

General IconGeneral
BrandGE
ModelLOGIQ S7 Pro
CategoryLaboratory Equipment
LanguageEnglish

Related product manuals