1126800 SmartPAC 2 with WPC Integration
Page 150 Chapter 2 Installing SmartPAC 2 and WPC
2. At the operator station, press the PRIOR ACT switch/indicator. The PRIOR ACT
indicator should illuminate and then turn off eight seconds later.
If the switch/indicator does turn off in eight seconds, go to step 3.
If the switch/indicator does not turn off within eight seconds, stop! Turn off the
press. Contact Wintriss Tech Support.
3. Press the PRIOR ACT switch/indicator and, before the light goes out, press both
RUN/INCH buttons. Release the RUN/INCH buttons after bottom dead center (BDC) of
the first stroke. The press should continue running.
If the press continues to run, go to the next step.
If the press stops, check the wiring and correct any problems. Re-run this test. If the
press still stops, contact Wintriss Tech Support.
4. At the operator station, press the TOP STOP button. Notice that the ram stops near top
dead center (TDC).
Go to the next applicable test.

Table of Contents

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the Honeywell SmartPAC 2 and is the answer not in the manual?

Honeywell SmartPAC 2 Specifications

General IconGeneral
BrandHoneywell
ModelSmartPAC 2
CategoryControl Unit
LanguageEnglish

Related product manuals