6. Include the project in the CMP.
In the SIMATIC Manager > select the multiproject folder > In the shortcut menu >
Multiproject > Insert into Multiproject > User Objects tab > select project > OK. Optionally:
Browse and navigate to the corresponding path.
7. Merge the Ethernet subnets.
In the SIMATIC Manager > select the multiproject folder > In the shortcut menu, >
Multiproject > Adjust Projects > select Ethernet > Execute > select subnet in the multiproject
> Merge with right arrow > OK > Apply.
8. Check if the S7 connection between the AS and the OS, which was deleted in the DMP, is
now in the CMP. Save NetPro.
– Open NetPro, select the CPU in the AS and check the S7 connection in the connection
table.
– Select the WinCC application on the OS and check the S7 connection in the connection
table.
9. Add the batch process cell and the ISA-88 type definition.
– In the Plant view of the SIMATIC Manager > Select the project > In the shortcut menu
> Insert new object > Batch process cell.
– Select the process cell folder in the Plant view > In the shortcut menu > Object properties
> "S88 type definition" tab > select object type "Process cell" > OK. The folder of the
batch process cell is given a light green color.
10.Check whether the name of the Batch process cell is identical to the name of the Batch
process cell at the MP level in all projects in the CMP.
In the plant view of the SIMATIC Manager, check the hierarchy names and the Batch
process cell names in the entire MP.
11.Compile and download the AS objects (CFC charts) and the OS objects of your multiproject.
12.Update the batch process cell, generate and propagate the batch types, merge the batch
instances, transfer the messages to the OS and load the batch data.
13.Update the batch data in the Batch Control Center (BCC).
Result
You have integrated the project back into the original CMP. You have made all the preparations
to start process mode in you project.
Rational engineering
8.5 Distributed multiproject engineering
SIMATIC BATCH V8.2
Operating Manual, 02/2016, A5E35958174-AA 237

Table of Contents

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the Siemens SIMATIC BATCH and is the answer not in the manual?

Siemens SIMATIC BATCH Specifications

General IconGeneral
BrandSiemens
ModelSIMATIC BATCH
CategoryControl Systems
LanguageEnglish

Related product manuals