E4 Series
Maintenance Manual
Power Plant
E4.08.04
Rev. 29
Page 309
71 -Maintenance Procedures
01-Jul-2020
Detail Steps/Work Items
Key Items/References
(10)
Put the blue isolation sleeve of the
inline crimp D-436-37 directly over
the splice crimp.
Apply heat to the inline crimp
isolation sleeve until it seals the
inline crimp barrel and the single
wires.
(11)
Put the chafing protection Roundit
2000NX5-5 over the repair kit
cable and the engine harness.
Decrease the length of the
Roundit, if necessary.
Make sure that the pigtail comes
out of the Roundit.
Make sure that the black plastic
backshell has the correct position.
(12)
Attach the repair kit cable with the
cable ties PLT1M-M30 and PLT4S-
M30.
Isolation sleeve
Roundit
Pigtail
Backshell