365-575-102 TroubleClearing:
Issue 8.0, July 2002 Page 1 of 2
TAP-129
Clear ‘DCC Startup in Progress’
NOTE:
The data communication channel (DCC) is starting up. This interaction between
the FT-2000 network elements takes from 5 to 7 minutes.
1. Wait 7 minutes or until the NE ACTY LED goes off.
2. Did the "DCC startup in progress" condition clear?
If YES, then continue with Step 3.
If NO, then go to TAP-108.
3. Is the NE ACTY LED lighted?
If YES, then go to Trouble Clearing: IXL-001.
If NO, then STOP! YOU HAVE COMPLETED THIS PROCEDURE.