365-575-102 TroubleClearing:
Issue 8.0, July 2002 Page 1 of 2
TAP-129
Clear ‘DCC Startup in Progress’
NOTE:
The data communication channel (DCC) is starting up. This interaction between
the FT-2000 network elements takes from 5 to 7 minutes.
1. Wait 7 minutes or until the NE ACTY LED goes off.
2. Did the "DCC startup in progress" condition clear?
If YES, then continue with Step 3.
If NO, then go to TAP-108.
3. Is the NE ACTY LED lighted?
If YES, then go to Trouble Clearing: IXL-001.
If NO, then STOP! YOU HAVE COMPLETED THIS PROCEDURE.

Table of Contents

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the Lucent Technologies FT-2000 OC-48 and is the answer not in the manual?

Lucent Technologies FT-2000 OC-48 Specifications

General IconGeneral
BrandLucent Technologies
ModelFT-2000 OC-48
CategoryNetwork Hardware
LanguageEnglish