365-575-102 Operation: NTP-004
Issue 8.0, July 2002 Page 5 of 6
Operation: NTP-004---+---DLP-501
|---DLP-524
|---DLP-536
21. Establish a login to all downstream nodes
(destination node and every intermediate node)
and update the STS-3 (or STS-1)
cross-connection map with the "new" source
node using the
CONFIGURATION-Enter-Crossconnection
-STS3 (or STS1) command. (The secondary
node was the source node for the 1-way-dri
cross-connection.) (To remotely establish a
login, refer to DLP-524.)
—
22. At the CIT, select
CONFIGURATION-Retrieve-Crossconnect
ion-STS3 (or STS1) and execute to obtain
an STS3 (or STS1) Cross-Connection Map
Report. Section 11 shows examples of reports.
—
23. Verify that the cross-connections in the report
match those in the operation instructions.
—
24. Discontinue the login at the primary node. (To
discontinue a remote login, refer to DLP-524.)
—
25. The necessary cross-connections have been
disconnected in this FT-2000 2-fiber ring
network. It no longer supports dual ring
interworking (DRI) operation with the second
SONET ring network.
—
DOITEMSBELOWINORDERLISTED........ FORDETAILS,GOTO