DLP-509: Detailed Level Procedure 365-575-102
Page2of2 Issue8.0,July2002
4. Did the remote operations center receive the correct response during the test?
If YES, then continue with Step 5.
If NO, then refer to the Installation Manual to correct the problem or con-
tact the group who did the installation.
5. Repeat Steps 2 through 4 for the remaining displays on the link.
6. Repeat Steps 3 through 5 for the other link.
7. STOP! YOU HAVE COMPLETED THIS PROCEDURE.