NTP-003: Acceptance 365-575-102
Page2of4 Issue8.0,July2002
NOTE:
Ensure that all slots, including the low-speed slots, are properly
equipped before initiating this test.
Verify the FT-2000 network elements are
connected in an FT-2000 point-to-point network
and are not looped back.
DLP-506
2. At the local FT-2000 end terminal, connect and
condition the craft interface terminal (CIT).
DLP-501
3. At the CIT, select SECURITY-Retrieve-Network
Element and execute to obtain a
Retrieve-Network Element Report to determine
the state of the Site 0 parameter. The site
parameter is used to differentiate the network
elements in a point-to-point network.
—
4. At the DSX-3 cross-connect panel or equivalent,
disconnect all DS3 inputs and outputs at the
local FT-2000 end terminal.
—
5. At the CIT, select CONFIGURATION-Update
and execute.
—
6. Establish a remote login to the remote FT-2000
end terminal and repeat Steps 3 through 5. An
assistant is required when Step 4 is performed
at the remote FT-2000 end terminal.
DLP-524
7. If required, and at the CIT, set SECURITY-Site 0
parameter to Yes at one end terminal and to No
at the other end terminal.
—
8. Verify the NE ACTY and the FE ACTY LEDs are
off at the local user panel.
—
9. Perform a system automatic turnup test on all
lines.
DLP-507
10. If required, test office alarm operation. DLP-504
DO ITEMS BELOW IN ORDER LISTED . . . . . . . FOR DETAILS, GO TO