NTP-005: Acceptance 365-575-102
Page2of2 Issue8.0,July2002
Acceptance: NTP-005---+---DLP-501
|---DLP-502
|---DLP-505
|---DLP-519
|---Acceptance: NTP-003 or
|---Acceptance: NTP-007
Inspect the FT-2000 repeater bay/shelf for obvious
damage.
—
2. Install an optical loopback with line buildout
between the IN and the OUT connectors of the
same OC48 REGENR circuit pack. Repeat this step
for any remaining OC48 REGENR circuit packs that
aretobetestedatonetime.
DLP-519
3. Verify the MN, NE ACTY, USE CIT, and PWR ON
LEDs at the user panel are lighted.
—
4. If required, connect and condition the craft interface
terminal (CIT).
DLP-501
5. Perform a local automatic turnup test on each OC48
REGENR circuit pack that is looped back.
DLP-502
6. Remove the optical loopback with the line buildout
from each OC48 REGENR circuit pack that is
looped back and reconnect the OC-48 line(s).
DLP-519
7. If required, perform provisioning at this time. DLP-505
8. This FT-2000 repeater bay/shelf has passed the
acceptance test and is now ready for the FT-2000
point-to-point network or the FT-2000 2-fiber ring
network (system) acceptance test.
Acceptance: NTP-003
or
Acceptance: NTP-007
DO ITEMS BELOW IN ORDER LISTED . . . . . . . FOR DETAILS, GO TO