DLP-507: Detailed Level Procedure 365-575-102
Page2of2 Issue8.0,July2002
Protection Access Upgrade
4.
!
CAUTION:
If this test is performed on a line other than the
protection line, then service will be interrupted.
NOTE:
Thistestcantakeupto5minutes.
At the local CIT, select FAULT-Test-Auto Turnup and
Line: P with Mode: System.
Response: The ABN and NE ACTY LEDs are lighted.
Did the report indicate "g" or "-" for each entry?
See Figure 2 for an example.
If YES, then STOP! YOU HAVE COMPLETED THIS PROCEDURE.
If NO, then refer to the Installation Manual or contact the group that did
the upgrade installation.
Figure 2 – Example of Test Auto Turnup Report - System Test (Protection Line
Only)
Lucent Technologies FT-2000 96-11-17 08:30:45 EST
M Test-Auto:P: COMPLD
/* Test-Auto Turnup Report - System Test
=============================================================
Line P: Transmit Receive
Direction Direction
gg
*/
;