365-575-102 Acceptance: NTP-009
Issue 8.0, July 2002 Page 5 of 12
23. To test path integrity for 2-way paths, repeat Steps
21 and 22 from opposite ends of each path.
—
24. At the FT-2000 primary node P, execute a manual
DRI switch for each path being tested. Use the
FAULT-Switch-Path-STS3(or
STS1)-Manual
command for the
appropriate line(s) and tributary(s).
—
25. Repeat Steps 21 through 23 for each path being
tested.
—
26. DO NOT RESET the DRI switch at node P at this
time. At FT-2000 primary node P' (P prime), execute
a manual DRI switch for each path being tested. Use
the FAULT-Switch-Path-STS3(or
STS1)-Manual
command for the
appropriate line(s) and tributary(s).
—
27. Repeat Steps 21 through 23 for each path being
tested.
—
28. At the FT-2000 primary node P, reset the manual
DRI switch for each path being tested. Use the
FAULT-Switch-Path-STS3(or
STS1)-Reset
command for the appropriate
line(s) and tributary(s).
—
29. Repeat Steps 21 through 23 for each path being
tested.
—
30. At the FT-2000 primary node P', reset the manual
DRI switch for each path being tested. Use the
FAULT-Switch-Path-STS3(or
STS1)-Reset
command for the appropriate
line(s) and tributary(s).
—