NTP-009: Acceptance 365-575-102
Page 6 of 12 Issue 8.0, July 2002
DO ITEMS BELOW IN ORDER LISTED . . . . . . . FOR DETAILS, GO TO
31. Verify that there are no alarm or status conditions in
the ring.
32. This completes testing path integrity (Figure 3).
33. The local FT-2000 ring has two DRI cross-connections to the outside. One DRI
cross-connection terminates in an external network and the other DRI
cross-connection terminates directly to test sets.
Verify that there are no alarm or status conditions in
thering(Figure4).
34. At the transmit end in the external network, insert a
verifiable signal into each path being tested.
35. At the receive test set, verify the detection of the
inserted signal on each path being tested.
36. To test path integrity for 2-way paths, repeat Steps
34 and 35 from opposite ends of each path.
37. At the FT-2000 primary node P, execute a manual
DRI switch for each path being tested. Use the
FAULT-Switch-Path-STS3(or STS1)-Manual
command for the appropriate line(s) and tributary(s).
38. Repeat Steps 34 through 36 for each path being
tested.
39. DO NOT RESET the DRI switch at node P at this
time. At FT-2000 primary node P' (P prime), execute
a manual DRI switch for each path being tested. Use
the FAULT-Switch-Path-STS3(or
STS1)-Manual command for the appropriate line(s)
and tributary(s).
40. Repeat Steps 34 through 36 for each path being
tested.
41. At the FT-2000 primary node P, reset the manual
DRI switch for each path being tested. Use the
FAULT-Switch-Path-STS3-Reset command for
the appropriate line(s) and tributary(s).