Operations and Maintenance Manual Preventive Maintenance Schedules
Version 1.2 - June 2004 10 - 9
7-DAY OR 5,000 WAFERS
PREVENTIVE MAINTENANCE SCHEDULE
(CONTINUED)
SUBJECT
ACTION
ESTIMATED TIME TO
COMPLETE
Grind Wheels
Check for wear and
damage; replace if
necessary.
Requires approx. 2 min. to
check.
Corrective procedure
(replace wheels, dress
wheels, reference wheels)
will take approx. 30 min.
Machine Operation
(1) Rotation Of Turrets
(2) Robot Handling
(3) Spin-Rinse Station
Check each item:
(1) Check operation.
(2) Check operation.
(3) Check operation.
(1) Requires approx. 10
min. to check.
(2) Requires approx. 10
min. to check.
(3) Requires approx. 10
min. to check.
Measurement Probe Housing
Measurement Probe Bellows
• Wipe down.
• Clean and apply
Molykote III (Dow
Corning ) lubricant.
Procedure requires approx.
10 min.
Measurement Probe Tip
Check for tightness
(secure fit).
Requires approx. 2 min. to
check. Corrective
procedure will take longer.
Spin-Rinse Chuck Brush
Check/adjust height.
Requires approx. 5 min. to
check. Corrective
procedure will take longer.