Chapter 3 ’Web User Graphical Interface’ — GUI Description
218 Electra VS
-
Version 05.10
User Manual - Rev. A
4.
Set the public job parameters as usual (see section
’Live SD-HD
Transcoder
on page 101).
5.
Enter the number of jobs to be created then start the jobs (see the
figure below).
Figure 3-181. Starting the jobs
Step 4: Add Hardware Resource (if Required)
Check the job state in the
Jobs list
panel.
Figure 3-182. Jobs status
If a job state is , add the necessary hardware resource (node or
SDI board for a server ).