ANSI Hardware Installation Manual Installing racks
Issue: 09 3HH-12893-AAAA-TCZZA 63
DRAFT
6 Cut open the moisture vapor bag with the shears and remove packing or bracing material.
7 STOP. This procedure is complete.
Procedure 7 To inspect equipment
1 Check the equipment items against the packing list.
2 Is the equipment packed in a container or a box?
a If in a container, go to step 3.
b If in a box, go to step 6.
3 Before removing the equipment from the container, check inside the container for parts that
may have become loose during shipment, and remove them.
4 Remove the equipment from the container, then raise the rack to a vertical position.
5 Remove the two transport brackets and eye bolts from the rack. Secure the rack to keep it
from falling over.
6 Check the equipment parts against the packing list.
7 Inspect the equipment for damage. The exterior and interior of equipment and component
parts must be free from grease, dirt, and corrosion.
8 If anything is missing or damaged, notify the transportation carrier and Nokia immediately.
Photograph all damaged equipment. Keep all inspection and packing documents for
reference.
Danger — Possibility of personal injury. Lifting heavy equipment
without the appropriate tools for material handling could result in physical
harm and/or damage the equipment. When lifting the racks, apply
appropriate pulleys or hoists and use the eye bolts.
Warning — Do not install damaged or dirty equipment, since this can
adversely affect the equipment.