Constraints for the brake test:
As a prerequisite for the brake test of a synchronized axis, all servo drives of 
the axis must be switched on and the brakes must be open. The test can only 
be performed if all relevant servo drives are switched on.
For slave drives for which the brake test has been disabled via 
MP_testBrakeCurrent, the current is adjusted so that the servo drive is not 
moved while the other servo drives of the synchronized axis are being tested.
Since the algebraic sign of the test torque cannot be determined until the 
drives are feedback-controlled and the brakes are open, an appropriate waiting 
time must be specified for the start of the brake test of synchronized axes. The 
time set in MP_vCtrlSwitchOnDelay (400929) is used for this. The value for 
MP_vCtrlSwitchOnDelay must equal the time that passes until the brake is 
really open after the controller has been switched on. The same time must be 
entered in MP_vCtrlSwitchOnDelay for all servo drives of a synchronized 
axis. For the CC61xx controller unit the time in MP_vCtrlSwitchOnDelay is 
taken into account each time the controller is switched on. 
In general, the following applies to the brake control: If the brakes are 
controlled by the PLC, and not by the inverters, the PLC module 9159 (drive 
controllers are switched off) transmits the status message to the PLC program 
regarding the closing of the brakes during the brake test.
Before performing the brake test, ensure via the PLC program that all servo 
drives of a synchronized axis are switched on and the holding brakes are 
open.
HEIDENHAIN recommends the sequential brake test of synchronized axes 
for all machines on which a brake test for synchronized axes made 
(MP_autoBrakeTest = off).
 Test the behavior of the PLC program and the brake test on the machine.