Step 2
Depending on the shelf and the power module installed, complete the necessary task:
Step 3
Connect the office ground to the NCS 2006 shelf. For detailed instructions on grounding, see the Electrostatic
Discharge and Grounding Guide for Cisco NCS 2000 Series.
Step 4
Complete the DLP-L22 Turning On and Verifying DC Office Power on the NCS 2006 Shelf, on page 218.
Step 5
Continue with the NTP-L11 Installing the Fan-Tray Assembly in the NCS 2006 Shelf, on page 296.
Stop. You have completed this procedure.
DLP-L18 Connecting Office Power (AC) to the NCS 2006 Shelf
This task connects AC power to the NCS 2006 shelf.Purpose
•
#2 Phillips Dynamometric screwdriver
•
Medium slot-head screwdriver
•
Small slot-head screwdriver
•
Wire wrapper
•
Wire cutters
•
Wire strippers
•
Crimp tool
•
Fuse panel
•
Ground cable 13.3-mm² (#6 AWG) stranded.
Tools/Equipment
•
NTP-L2 Mounting the Brackets in ANSI
Configuration , on page 163.
•
NTP-L5 Opening and Removing the Standard
Door of the NCS 2006 Shelf , on page 252.
•
Connect the chassis to the office ground. For
detailed instructions on how to ground the
chassis, see the Electrostatic Discharge and
Grounding Guide for Cisco NCS 2000 Series .
Prerequisite Procedures
RequiredRequired/As Needed
OnsiteOnsite/Remote
NoneSecurity Level
Cisco NCS 2000 Series Hardware Installation Guide
204
Connecting Power and Ground
DLP-L18 Connecting Office Power (AC) to the NCS 2006 Shelf