Step 3
Repeat for each cable. Refer to ITU-T G.813 for rules about provisioning timing references.
Step 4
Return to your originating procedure (NTP).
DLP-L28 Installing Timing Wires in NCS 2006 - ETSI
This task installs the timing cables on the NCS 2006
ECU module for ETSI.
Purpose
75-ohm coaxial cable with a DIN-1.0/2.3 miniature
coaxial connector. The PID for the BITS IN/OUT
cable is 15454-M-TMGCBL=
Tools/Equipment
NTP-L8 Install the NCS 2006 ECU and ECU-S
Modules, on page 277
Prerequisite Procedures
As neededRequired/As Needed
OnsiteOnsite/Remote
NoneSecurity Level
Procedure
Step 1
Connect the clock cable to the corresponding ECU module connector using a coaxial cable with DIN-1.0/2.3
miniature coaxial connectors. The following figure shows the ECU module ETSI BITS connectors.