DLP-L1 Verify the NCS 2006 Shelf for AC Power Module Installation
This task verifies the shelf for AC power module
installation.
Purpose
NoneTools/Equipment
DLP-L62 Unpacking and Verifying the Shelf , on
page 20
DLP-L63 Inspecting the Shelf, on page 22
Prerequisite Procedures
RequiredRequired/As Needed
OnsiteOnsite/Remote
NoneSecurity Level
Procedure
Step 1
Verify the position of the mechanical locking system on the rear side of the chassis. To use the AC power
module, the screw must be close to the AC silk-screen text (see the figure below).
Figure 104: AC Power Module Installation
—
Rear Side of the NCS 2006 Shelf
Step 2
Loosen the screw and move it to the left position (towards the AC silk-screen text).
Step 3
Tighten the screw again to a torque value of 4 in-lb (0.45 N-m).
Cisco NCS 2000 Series Hardware Installation Guide
167
Mounting the Brackets on NCS 2006 Shelf
DLP-L1 Verify the NCS 2006 Shelf for AC Power Module Installation