12.11.1 Commissioning
In the following, the required steps are described to control the device as EtherNet/IP adapter.
Precondions
The control unit (CU) of the inverter is provided with EtherNet/IP (from rmware 02.01).
The device is networked as EtherNet/IP Adapter with an EtherNet/IP Scanner and, if neces-
sary, further EtherNet/IP nodes.
Typically, an EtherNet/IP network consists of segments that contain point-to-point con-
necons in a star conguraon.
See also "Typical topologies" under: EtherNet/IP ^ 395
An Engineering PC with the programming soware »RSLogix™ 5000« (from version 20) is
connected to the Scanner.
Current device descripon les for EtherNet/IP are available.
Download of EDS les
The les are installed via the "EDS Hardware Installaon Tool" of the »RSLogix™ 5000«.
Allen-Bradley control systems do not need any EDS les to add devices to their congu-
raon.
An »RSLogix™ 5000« project has been created and is in the oine state.
The CPU and Ethernet adapter of the PLC (Scanner) have been congured.
All EtherNet/IP nodes are supplied with voltage and are switched on.
Commissioning with »RSLogix™ 5000« (from version 20)
How to congure the network:
1.Congure IP communicaon.
1. Make IP basic sengs at the Engineering PC.
The PC with the programming soware »RSLogix™ 5000« must be in the same network
as the devices to be congured.
2. Set IP address of the inverter (adapter) via rotary encoder switch and parameter
0x23A1:001 (P510.01).
3. Set subnet mask: 0x23A1:002 (P510.02)
4. Set gateway address: 0x23A1:003 (P510.03)
The conguraon of the IP communicaon is now completed.
2.Acvate network control in the inverter.
1. Acvate network control: 0x2631:037 (P400.37) = "Network control acve [114]"
2. Set network as standard setpoint source: 0x2860:001 (P201.01) = "Network [5]"
If a dierent standard setpoint source is set and the network control is acvated, a
change-over to the network setpoint is possible via the AC Drive control word 0x400B:
001 (P592.01).
The network control is now acvated.
3. Save parameter sengs: 0x2022:003 (P700.03) = "On / start [1]"
3.Execute I/O conguraon with »RSLogix™ 5000« (version 20).
1. Start the »RSLogix™ 5000«.
2. Open or recreate a »RSLogix™« project.
3. Congure the cyclic data transfer (Implicit Messaging).
4Process data transfer ^ 400
4Customised
conguraons ^ 330
4. Congure the acyclic data transfer (Explicit Messaging).
4Parameter data transfer ^ 404
The I/O conguraon is now completed.
The conguraon of the network is now completed.