Starting Up HiPath 3000
P31003-H3550-S403-4-7620, 02/05
5-6 HiPath 3000 V5.0, HiPath 5000 V5.0, Service Manual
start_h3.fm
Starting Up HiPath 3800
5.2.3 Carrying Out a System Reload
After supplying the system with power, you must carry out a system reload.
Procedure
Press and hold down the reset switch for at least 5 seconds (FAIL LED (red) goes out). If you
do not hold down the reset switch for a full 5 seconds, the system may perform a reset rather
than a reload or may not reload properly.
>
The reset/reload switch is tested by a Field Programmable Gate Array (FPGA). This
FPGA is loaded by the processor when starting up the HiPath 3800 and is only fully
functional after the loading process is complete. If the reset/reload switch is activated
during loading, then it is not possible to evaluate the cause of the restart. For this
reason, the reset/reload switch may only be activated after the system startup (green
Run LED lights up).

Table of Contents

Other manuals for Siemens HiPath 3000

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the Siemens HiPath 3000 and is the answer not in the manual?

Siemens HiPath 3000 Specifications

General IconGeneral
BrandSiemens
ModelHiPath 3000
CategoryTelephone
LanguageEnglish

Related product manuals