Merge two Groups via Visual Alignment
Now the Stations taken in the courtyard are stored in two separate Groups. But there is so far
no connection between Group 1 and Group3. In the next step we will create a visual alignment
between Station 4 (Group1) and Station 5 (Group3). This will then create a link between the two
Groups and will allow us to merge all six Stations into one single Group.
Figure 33
•
If not already open, re-open
Registration 1
from Cyclone
Navigator
•
Go into the Tab
ScanWorld’s
Constraints
•
Expand
Groups 1
+
3
•
Highlight
Station-004
and
Station-005
•
Open
Visual Registration |
Visual Alignment
This will bring up the Visual Alignment window with the selected Stations loaded. Proceed to
visually align and optimize the alignment as in the previous step and use the created constraint
to merge
Group 3
into
Group 1
:
Figure 34
•
Visually align the Scans
Take particular care to also align them
vertically
•
Tools | Optimize Constraint