29
ALIGN
& FIX SCREWS
Step 18: Install the Flexible Shaft (item 5).
Step 19: Install the curved sheet metal Exit Paper Guide (item 7) with Idler Roller “4” Screws.
Start all “4” screws, (2 on front and 2 on back) then tighten.
Step 20: Connect the Sensor Wire Harness at the top rear of the Exit Paper Guide.
Step 21: Install the J2 Shaft back into place by inserting it first into the front, then the back.
INSTAL j2 SHAFT
ASSEMBLE BACK
Step 22: Close the J2 Flipper Latch.
Repeat the test of rotating the pulleys to ensure smooth rotation of the Idler Rollers.
Step 23: Attach the J2 Shaft Spring
Install the front E-Ring to secure J2.
Step 24: To install the Idler Aligner Paper Guide.
A. Hold it loosely in place.
B. Press the Nylon Flange Bearings into place, through both pieces of sheet metal,
with the Flange to the inside.
C. Slide the Shaft through the front of the machine, while holding the Nylon Flange
Bearing in place.
D. Secure with “2” E-Rings on the inside of the bearing.
E. Inspect by pressing in on the bottom area of the sheet metal for:
#1 should see a slight deflection of each Idler Roller as you press,
#2 as you press, you can turn the Pulley’s at the rear of the StreamPunch and
see the Idler Rollers rotate smoothly.