General Procedures and Information 09/11/2018 GBC AdvancedPunch Pro
6-74
GP 6.22 Solenoid Cleaning and Inspection
Do the following to inspect and clean the Solenoids every 1000K cycles.
1. Open the front the door and insert an Interlock Cheater into the
Punch Door interlock Switch SW4 (PL 2.2).
WARNING
Moving Parts, keep hands clear of nips and the belts when the
Interlock Cheater is inserted. See Section 0, page vii for other
languages.
2. Do GP 6.2.10 SOLENOIDS Procedure to activate and deactivate the
affected solenoid.
When the solenoid is not activated, the idler roller should be able to
rotate freely and in turn will drive the drive roller.
not activated
fully activated
When the solenoid is fully activated, the idler roller should completely
lift off and not be able to drive the drive roller.
NOTE: Disengaging solenoid modules need to be replaced every 5
million cycles.
3. Clean the solenoid and surrounding area with a vacuum cleaner and
canned air.
1. Make sure the solenoid is clean and dry.
2. Inspect for dirt or obstructions, wear or a damage spring.
3. Inspect and ensure the Solenoid linkage moves freely. Press linkage
down and release. Linkage should return.
Note: Do not apply lubricants to the solenoid or linkage.