CCW-R-2**B INSTRUCTION MANUAL 12 INSTALLATION
12-7
12.4 Installation Procedure
The overview for the weighing machine installation procedure is described below.
For details of each procedure, refer to the following reference section.
After installing the weighing machine, perform check and adjustment of the installation
condition.
( 12.5 Check and Adjustment After Installation)
Table 12-2 Installation Procedures
Unpacking the weighing machine ( 12.4.1 Unpacking Procedure)
Checking the weighing machine ( 12.4.2 Checking Weighing Machine)
Carrying in and installing the weighing machine
( 12.4.3 Carrying in and Installing the Weighing Machine)
Connecting the power cable and remote control unit
( 12.4.4 Connecting Power Cable and Remote Control Unit)
Installing the timing hopper frame
( 12.4.5 Installing Timing Hopper Frame)
Installing the signal wire for the timing hopper
( 12.4.6 Connecting TH Signal Wire)
<Installing components to the main body>
Installing the timing hopper ( 12.4.7 Installing Timing Hopper)
Installing the discharge chute ( 12.4.8 Installing Discharge Chute)
Installing the collection chute ( 12.4.9 Installing Collection Chute)
Installing the radial trough ( 12.4.10 Installing Radial Trough)
Installing the dispersion table ( 12.4.11 Installing Dispersion Table)
Installing the booster hopper ( 12.4.12 Installing Booster Hopper)
Installing the weigh hopper ( 12.4.13 Installing Weigh Hopper)
Installing the pool hopper ( 12.4.14 Installing Pool Hopper)
Connecting to the interlocking device