CSIP Level 1 Performance Tests: Introduction
6Performance Tests
Introduction
This section contains a series of performance tests to be performed on the system following
installation, upgrade, or repair. The purpose of these tests is to verify the correct operation of
the system (hardware and firmware). The Performance Test Checklist included at the end of this
section can be used to ensure that all tests are performed.
The major test sections in this procedure are organized to follow a logical progression through
each of the major system modes. It is not a requirement to perform the sections in any particu-
lar order. However, it is best to perform the tests in their written order to promote a thorough
and consistent testing process.
For all of the tests in this section, verify image quality and that the image is free of artifacts.
WARNINGS • System performance must be verified after installation, after every repair involving PCB or
power supply module replacement, and during every preventive maintenance inspection. If
measurements are inaccurate, misdiagnosis may result in harm to patients.
• Wrist straps should not be worn when working on a system with the power turned on. The
+5 Vdc supply is a very-high current supply. Use caution when troubleshooting.
NOTE To ensure proper system operation, turn on all OEMs prior to checking system func-